Wednesday, August 4, 2021

New #7 Bridge

 About two months ago, an accident occurred off of 115th street on the south end of the golf course. The vehicle came through the fence and down into the creek near the 7th green. It came to a hard stop as it careened into the bridge that runs over the pond/creek at 7 green, knocking the bridge three feet off its footings and essentially ruining the bridge. Lucky for us, that bridge was in need of being replaced. Huge thanks to the Parks & Rec for getting us a new bridge that definitely isn't going anywhere!! Pictures below will show you the construction of our new bridge.....

This is the old bridge after it was struck by the vehicle and moved off footings

Old bridge being torn out

Old bridge removed

New 48" culverts being installed

Two new culverts installed

48" culverts will be more than plenty to handle the creek waters

New bridge taking shape

New bridge framed and ready for concrete

Concrete being poured

New bridge completed!!

Hole 7 bridge



New #7 Bridge